Quality Control · October 10, 2026 · Hold-Tech Engineering Team

First Article Inspection Explained: Why It Protects Your Production Run

A first article inspection validates that your supplier's process produces parts that meet the drawing before full production. Here is how FAI works and what to ask for.

First Article Inspection Explained: Why It Protects Your Production Run

What a First Article Inspection Is

A First Article Inspection (FAI) verifies that the manufacturing process — before full-rate production — produces a part that fully conforms to the drawing and specification. It is the supplier's evidence that the process is capable, and it is your first line of defense against a bad production run.

The result is a written report that documents, dimension by dimension, that a representative part matches the print. For aerospace and defense work it is typically produced to AS9102; many OEMs request an equivalent FAI for commercial and industrial parts even when a formal standard is not mandated.

What an FAI Report Contains

  • Part accountability: drawing number, revision, material certified to the print, finish, and special process records.
  • Characteristic-by-characteristic results: every dimension, tolerance, and note on the drawing, with measured values and pass/fail.
  • Material certification: mill test certificate or material cert traceable to the purchase of the raw stock.
  • Inspection tools and methods: which gauges, CMM program results, and instruments recorded each dimension.
  • Approvals: inspector, review engineer, and (in AS9102) the supplier's quality manager sign-off.
  • Nonconformance findings: any characteristic that did not meet print, the disposition (use-as-is, rework, scrap), and the corrective action.

When an FAI Is Required

  • First production run of a new part number.
  • After any change to design, material, process, tooling, or a major supplier change.
  • After a lapse in production long enough that the process was reset.
  • When the customer contractally requires an FAI (common in aerospace, defense, medical, and automotive tiers).

How Inspection Methods Differ

A good FAI does not just report values — it uses the right tool for each feature:

Feature TypeTypical ToolingNotes
Outer/inner diameters, critical distancesCMM (coordinate measuring machine)Programmed for repeatability across runs
Small bores, slotsPin/plug gauges, bore gaugesFast, reliable for go/no-go
Surface finishProfilometer / surface roughness testerRa compared to print callout
ThreadsThread plug/ring gauges or opticalVerify pitch, class, and profile
Textured/geometric featuresOptical or laser scanner for GD&T surfacesGD&T datum references tracked
HardnessHardness tester (Rockwell/Brinell/Vickers)Per material spec zone

Reading an FAI Report Critically

  • Confirm the drawing revision matches your released revision — an FAI on the wrong revision protects nothing.
  • Check that every dimension listed on the print appears in the report. Missing characteristics are a red flag.
  • Look at the margin, not just pass/fail. A dimension that measures at 90% of its tolerance is a warning that process drift could push it out on the next run.
  • Verify material cert traceability matches the heat/lot code claimed.
  • Keep the signed FAI as your record — it is the baseline your supplier's process must maintain.

FAI at Hold-Tech

Every production order we machine starts with part accountability review, and our inspectors produce FAI-style documentation with CMM and calibrated gauges for the dimensions that matter. When a drawing carries a tight GD&T scheme, we build the inspection program before the first part comes off the machine so the first article is documented, not improvised.

Request an FAI or FAI-style report on your next machined part by contacting operator@hold-tech.cn — it is the cheapest insurance against a bad production run.

FAI first article inspection quality control AS9102 CMM

Ready to manufacture your parts?

Send your drawings to operator@hold-tech.cn or call +86-186-60386138 for a quote with DFM feedback within 24 hours.